A power station supplies the peak load of 60 Mw, 40 MW and 70 MW to three localities. The annual load factor is 0.50 p.u. and the diversity factor of the load at the station is 1.55. The maximum demand on the station and average load respectively will be 

1 Answer

Answer :

A power station supplies the peak load of 60 Mw, 40 MW and 70 MW to three localities. The annual load factor is 0.50 p.u. and the diversity factor of the load at the station is 1.55. The maximum demand on the station and average load respectively will be 103.2 MW, 51.61 .

Like 0 like

Related Questions

Description : At an industrial sub-station with a 4 MW load, a capacitor of 2 MVAR is installed to maintain the load power factor at 0.97 lagging. If the capacitor goes out of service, the load power factor becomes (A) 0.85 (B) 1.00 (C) 0.80 lag (D) 0.90 lag

Answer : At an industrial sub-station with a 4 MW load, a capacitor of 2 MVAR is installed to maintain the load power factor at 0.97 lagging. If the capacitor goes out of service, the load power factor becomes  0.80 lag

Description : A generating station has a maximum demand of 50 Mw, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded. The daily energy produced will be

Answer : A generating station has a maximum demand of 50 Mw, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded. The daily energy produced will be 720 MW.

Description : A 3-phase 11 kV generator feeds power to a constant power unity power factor load of 100 MW through a 3-phase transmission line. The line-to line voltage at the terminals of the machine is maintained constant at 11 kV. The per ... 11 kV is  (A) 100 MVAR (B) 10.1 MVAR (C) -100 MVAR (D) -10.1 MVAR

Answer : A 3-phase 11 kV generator feeds power to a constant power unity power factor load of 100 MW through a 3-phase transmission line. The line-to line voltage at the terminals of the machine is maintained ... load to increase the line-to-line voltage at the load terminals to 11 kV is -10.1 MVAR

Description : A single phase 60 Hz generator supplies an inductive load of 4500kW at a power factor of 0.80 lagging by means of a 20 km long overhead transmission line. The line resistance and inductance are 0.0195 ohm and 0.60 mH ... voltage regulation of the line.  (A) 12.59% (B) 16.34% (C) 32.68% (D) 41.15% 

Answer : Answer is C